Patio final walkthrough checklist

What to test before you sign off and make the last payment.

Updated September 18, 2026

Find a Landscaping Company What it costs

Written by HyreYard Research Desk Research and fact checking

The short answer

Walk a new patio with the contractor before the final payment and check five things: water runs away from the house, the surface is flat with no rocking units, joints are full, edges are restrained, and the site is cleaned up with paperwork in hand. Bring the written scope, a level, a hose or bucket of water, and your phone for photos.

Two tests carry most of the weight. Slope: code summaries of the International Residential Code ask for hard surfaces within ten feet of a foundation to fall at least 2 percent away from the building, so pour water near the house and watch where it goes.

Edges: the Interlocking Concrete Pavement Institute’s inspection checklist calls for edge restraints to be in place, because pavers without them creep apart.

Write every defect on a punch list, agree dates to fix them, and hold the final payment until they are done. The FTC’s home repair advice says to make the final payment only when the work is finished to your satisfaction.

Surface and slope

Water runs away from the house

Pour water near the wall. It should travel away and off the patio without pooling. Puddles that remain after a few minutes are a defect.

Slope stated in the scope is met

Lay a four-foot level pointing away from the house. A 2 percent fall is about a quarter inch per foot; compare with what the contract states.

No rocking or sunken units

Walk the whole surface, including edges and corners. Any paver or slab that moves underfoot needs lifting and resetting.

No lips at joints

Run your palm or shoe across joints. Raised edges are trip points.

Doors still open

Check that the finished surface sits below door thresholds and weep screeds, so water and the door both clear.

Joints, edges and cuts

Joints filled to the right level

Joint sand should be full and, for polymeric sand, set without haze on the surface. See paver joint sand.

Edge restraint in place

Find the edge restraint along every open side. Lift a little soil at the edge to see it.

Clean cuts at borders

No small slivers at edges or around drains; the installer’s minimum piece size should be met.

Pattern matches the agreed plan

Pattern, color blend and border are as drawn or sampled.

Haze, stains or chips

Efflorescence, mortar or polymeric haze, and chipped units photographed and listed.

Around the patio

Lawn and beds restored

Ruts from machines raked and seeded or sodded as the scope says.

Downspouts reconnected

Any extension removed during work is back, discharging away from the patio.

Irrigation tested

Run each zone near the patio. Heads moved or broken during excavation are repaired. See irrigation.

Walls and steps

Caps glued and level, steps consistent in height, drain outlets from walls visible. See retaining wall ideas.

Debris removed

Leftover pavers, pallets, sand, cement bags and cut waste gone, unless you asked to keep spare pavers.

Paperwork before the final payment

Workmanship warranty in writing

Length, what it covers (settling, joint loss), and how to claim. See hardscape warranty.

Manufacturer product details

Paver or block product name, color and lot, so repairs match later.

Permit closed

If a permit was pulled for walls or covers, the final inspection is passed.

Lien releases

Releases from the contractor and major suppliers for the amounts paid.

Care instructions

When to re-sand or seal, and what de-icers or cleaners to avoid.

What to bring

The written scope and drawing

The walkthrough checks the job against what was agreed, not against memory. See landscaping estimates.

A four-foot level and a hose or bucket

For the slope and water tests.

Your phone

Photos of each defect, with something for scale.

If something fails the walkthrough

1
Write the punch list on site

Each defect, its location and a photo. Both of you sign or confirm by email.

2
Agree a fix date

Specific dates, and whether the crew returns as one visit.

3
Hold back the final payment

Keep the final payment until the list is closed. A payment schedule tied to milestones makes this routine; see landscaping deposits.

4
Re-walk after the fix

Repeat the water test on any area that was relaid.

Your inquiry

Tell us about the work

Nothing goes to a landscaping company unless you agree.

Free, with no obligation: a person at HyreYard reads your request and replies by email. Matching is not live yet, so this is not a quote, and nothing goes to a landscaping company unless you agree. If a tree or limb is on a power line, stay away and call the utility.

Find a Landscaping Company

One short form: your address and how to reach you. A person at HyreYard reads it and replies.

Your details

We reply to every inquiry. Nothing is passed on to anyone you have not asked us to contact.

Questions

When should I do the final walkthrough on a patio?
After the crew says it is finished and before the final payment. A day after rain, or with a hose test, shows drainage.
Should a new paver patio hold water?
No. Water should run off within minutes. Standing puddles mean low spots or insufficient slope.
What should I do if pavers rock after installation?
List them on the punch list. Rocking units usually need lifting, bedding corrected and resetting, which is a warranty item.
How much should I hold back until the punch list is done?
Hold the final scheduled payment. Your contract should state the payment tied to completion.
Is white haze on new pavers a defect?
It can be efflorescence or residue from joint sand. Ask the contractor what it is and how it will be cleaned; note it on the punch list.

Written and audited by

HyreYard Research Desk

Primary-source research, data analysis and fact checking

We are a research desk, not a landscaping company. We read the statute, the municipal code, the water-district rule or the federal soil file ourselves, and we publish the figure with the document it came from and the date we retrieved it.

Where a number cannot be traced to a primary source, we publish the shorter page and say what we could not verify. This desk is new.

The counts below are what we can already stand behind, and every one of them is counted from the studies on this site.

255
source documents cited, each linked
112
government (.gov) domains among them
258
citations carrying a retrieval date
10
research studies published

How this desk works

  • Primary sources only. A rule comes from the statute, ordinance, board or agency that issued it, cited by section, with the URL and the retrieval date. We do not cite a blog that cites a code.
  • Coverage is a number. A table titled to fifty states has fifty sourced rows. A table of cities is titled to the cities we actually read. Gaps are published as gaps.
  • Company counts stay inside seven states. Texas, Arizona, Washington, California, Oregon, Florida and North Carolina. Texas is the largest roster on the weakest evidence, a self-reported NAICS sales-tax permit, because Texas licenses no landscaper. National claims rest on federal or state agency data, never on our counts.
  • Fact, calculation, analysis and recommendation stay labeled. "According to…" is a source. "HyreYard analyzed… and calculated…" is ours. "This suggests…" is interpretation. We do not present our reading as something the source stated.
  • We do not landscape, irrigate, plant, cut trees or pull permits, and we take no payment for placement, ranking or a favorable mention. Nobody buys a position on this site.

Authorship on this site is organizational: the analysis belongs to the desk rather than to a named individual, and we do not publish credentials we do not hold. Our editorial policy sets out how we source, date and correct what we publish.

Sources & retrieval dates

ICPI — Construction Inspection Checklist, Edge restraints in place; no pavers on frozen base. Retrieved October 2026.
InterNACHI — Slope of Grade, IRC summary: impervious surfaces within 10 ft of foundation slope 2% away. Retrieved October 2026.
FTC — Home repair advice (2004), Final payment when work is finished to your satisfaction. Retrieved October 2026.
Workyard — Final Walk Through Checklist (PDF), Debris removed; warranties accounted for. Retrieved October 2026.